Executive Summaries Oct 1, 2020

Regulations under Bill 102: A New Approach Based on the Environmental Risks of Each Project

On September 2, 2010, the Government of Québec published in the Gazette officielle du Québec the 23 regulations and amendments to existing regulations intended to ensure, as of October 31, 2020, the near-complete implementation of Bill 102, adopted on March 26, 2018, which introduced a new unified environmental authorization scheme in the Environment Quality Act (the “EQA”).

These new regulations were adopted following the publication of as many draft regulations published in 2018 and 2020, and after intense discussions with stakeholders likely to be affected by this new regulatory regime. These new regulations will take effect on December 31, 2020. Over 200 submissions from citizens, groups, municipalities and businesses were received in response to the draft regulations published in 2018, prompting the  to resume work on the new regulations and publish new draft regulations on February 19, 2020, for public consultation. These new regulations were prepared through a "co-creation" exercise with the stakeholders affected by the new regulations.

According to the press release issued on September 2, the new regulations will reduce by approximately 30% the number of ministerial authorizations to be filed each year. It also mentions that the receives 5,000 applications for authorizations annually. However, the 2017/2018 annual report states that the processed 4,034 applications for certificates of authorization and the 2018/2019 annual report indicates that the same department processed 3,732 applications for certificates of authorization. Experience will show the real impact of these new regulations on the number of environmental authorizations issued annually by the .

Systematization of a New Administrative Approach

The new regulations are intended to implement a new approach to the administrative management of projects likely to have an environmental impact. Under this new management process, projects likely to produce environmental effects are divided into four categories, based on the significance of the environmental risks associated with each project.

Thus, projects with so-called “high” environmental risks are subject to an environmental impact assessment and review procedure and may potentially be brought before the .

“Moderate” environmental risk projects are subject to an environmental authorization issued by the or an official to whom the Minister has delegated the authority to issue such authorizations.

Projects with “low” environmental risks will be subject to a declaration of compliance by the project proponent.

Finally, projects with “negligible” environmental risks will benefit from an exemption and may be carried out freely provided that they comply with the guidelines that were designed for the implementation of projects benefiting from such an exemption.

A Strong and Detailed Regulation

The main regulation relating to environmental authorizations is called the Regulatory scheme applying to activities on the basis of their environmental impact. This 370-article regulation lists and describes the projects subject to an environmental authorization, the projects subject to a declaration of conformity and the exempted projects. It also prescribes the terms and conditions relating to the renewal, assignment, suspension or revocation (at the request of the holder) and termination of an authorization as well as the terms and conditions relating to the declaration of background that the applicant for authorization must produce. This regulation is intended to be the reference regulation for environmental authorizations in Québec law.

Activities With “Moderate” Environmental Risks

The new regulation specifically lists approximately 40 categories of activities deemed to be “moderate” environmental risk activities which will require ministerial authorization before being undertaken. These are quite similar to those listed in the draft regulations originally published for public consultation on February 14, 2018.

The projects listed in the regulation are not the only ones subject to the environmental authorization requirement since the second paragraph of section 22 of the applies this requirement to any other activity likely to release contaminants into the environment or modify its quality, including industrial activities, unless such an activity benefits from one of the general exemptions provided for in sections 51 to 54 of the new regulation.

For projects requiring a ministerial authorization, the regulation sets out the general and specific information that the project proponent must submit to the in order to obtain the required ministerial authorization. The regulation also specifies the types of projects that will be subject to the new “climate test” required by Bill 102. A background declaration and the fees required by the ministerial order on this matter must also be included with the application for authorization.

“Low” Environmental Risk Activities

The new regulation specifically lists "low" environmental risk projects that, instead of being subject to ministerial authorization, are eligible for a declaration of compliance to be filed with the by the project proponent at least 30 days before the project begins. The project must begin within two years of the filing of the declaration of conformity. In reality, for 28 of the 40 categories of activities subject to ministerial authorization, the regulations indicate which activities are eligible for a declaration of conformity provided that certain technical parameters and conditions, as described in detail in the regulations, are met. If the activity is carried out without complying with the conditions, restrictions or prohibitions set out in the regulations, the activity will be deemed to be carried out without a ministerial authorization, making the initiator of the activity liable to remedies, sanctions, fines and any other applicable administrative measures in the event of non-compliance with the .

In this regard, it should be noted that the carrying out of an activity without a ministerial authorization required by the makes the offender liable to administrative monetary penalties of $5,000 or $15,000, depending on whether the offender is an individual or a legal entity, or a minimum fine of $5,000 or $15,000, depending on the same circumstances.

It is worth mentioning that the regulations clearly specify the technical and other information to be included in the declaration of conformity. As well, fees payable under the Ministerial Order dealing with this matter must be included with the declaration of conformity.

“Negligible" Environmental Risk Activities

Finally, the new regulation sets out, for 29 of the 40 categories of projects, a whole series of activities with environmental risks deemed "negligible" which will be exempted from any prior administrative formalities and can therefore be freely carried out provided that they comply with all the technical parameters relating to the carrying out of the activity benefiting from an exemption.

In particular, exemptions provided for in the regulation include, in new wording, regulatory exemptions that had already been provided for since 1975 with respect to section 22 of the , as well as the so-called “administrative” exemptions that had been developed by officials without having been the subject of a regulatory instrument. Indeed, the routinely applied these “administrative” exemptions and informed applicants that these activities, thus exempted, could be carried out without a certificate of authorization under section 22 of the .

For 25 years, BCF’s mission has been to support Canadian businesses. We know the issues you face and our Environmental Law team is available to help you use the resources at your disposal. Do not hesitate to contact one of our members should you need advice or support.

Stay on the lookout!

Subscribe to our communications and benefit from our market knowledge to identify new business opportunities, learn about innovative best practices and receive the latest developments. Discover our exclusive thought leadership and events.

Subscribe

You would also like

Four of Our Professionals Contribute to the Chambers Real Estate 2025 Guide

BCF Recognized in the 2025 Edition of Benchmark Litigation Canada

lexpert

27 BCF Professionals Stand Out in the Canadian Legal Lexpert Directory 2025

Lexology

6 BCF Professionals Recognized in Lexology Index Canada 2024

contrat

RBQ Resumes Investigation into Armoires PMM

Entrepreneurship forum

Entrepreneurship Forum: Vision 2025

construction site

Preservation of the right to a construction legal hypothec: What Is the Impact of a Contract Termination?

BCF Stands Out in Legal 500 Canada

Tech Forum 360

Tech 360 Forum: Growth and Inflection Points

Contractor Liability for Ground Defects Leading to Loss of the Work

Prospera: Québec’s Economic Barometer

Canada's Best Managed Companies: BCF Recognized for 17th Consecutive Year

Contruction meeting

Site extensions : how do you build a solid claim?

livres-echelle

Jean Piette contributes to a landmark case before the International Court of Justice

deal

Damotech Receives Strategic Investment from Mountaingate Capital in its Transaction with Mac Rak

papier signe

Novolecs Acquires Assets of Stace in Québec

court

Victory for Ressources Utica and its Subsidiaries: The Superior Court Suspended the Application of Provisions of a Provincial Law Adopted in 2022

Victory for Développements St-Antoine as the Expropriated Party is Fully Compensated

Contractors: Why Is It Important for You to Be Directly Involved in the Work?

new-partners-2024

BCF Has Appointed Three New Partners

andre-ryan-client-choice

André Ryan Wins the Prestigious Client Choice Awards for 2023

Construction Work: An Additional Liability for Owner-Employers

Non-compliance with the Contractual Claims Procedure: a Fatality for Contractors?

Who’s Who Legal : 5 BCF Professionals Stand Out

BCF extends its Partnership with the Canadian Association of Black Lawyers to a Third Year

Annie-Claude Trudeau and Audrée Anne Barry, Co-Authors of the 2023-2024 Annotated Code of Civil Procedure

house-near-river

Watercourses and Ditches: What are the Risks of Building your Home Close to One of Them?

pierre-nuage

Contractors : Are you Responsible for the Quality of your Materials?

newspaper

Le Devoir is now a Registered Journalism Organization

The Risks of Miscommunication on a Construction Site

Chambers Canada Ranking: Five of our Lawyers Recognized

Photo of Julie Doré

Julie Doré Takes Over Management of The BCF Business Law Firm

Three Up-and-Coming Lawyers Join BCF

What is New in Terms of Liability for Loss of the Work?

Prospera – Quebec Economic Barometer

34 Professionals Stand Out in the Canadian Legal Lexpert Directory 2023

Julien Tricart, Member of the Meritas Sports Law Group

Non-Compliance Clauses in Construction Contracts: When Do They Apply?

Court Alternatives to Add to Your Toolbox

Pride Month: Let’s Create an Inclusive Future

Distillerie des Cantons-de-l'Est inc. Wins Its Case Before the Commission de Protection du Territoire Agricole du Québec

Canada’s Best Managed Companies: BCF Recognized for 16th Consecutive Year

Benchmark Litigation Canada's 2023 Edition: BCF Stands Out Once Again

Carbon Neutrality in Canada – Where Are We Now?

Businesses: Why Should You Hire an Environmental Mediator?

Climate Change as a Strategic Opportunity: Adaptation and Eco-Responsibility for Businesses

Directors and Officers: What Is Your Environmental Liability?

The non-profit organization SOLIDES gets its hands on 363 doors in a major transaction to curb the housing crisis in Drummondville

Every Woman Counts

Strategic Forum on the Role Played by Businesses in the Fight Against Climate Change

BCF Partners with the Canadian Association of Black Lawyers to Promote Diversity in Québec Law Faculties

BCF's More Inclusive Approach: Improved Parental Leave

Shaun E. Finn Appointed to the Superior Court of Québec

How to Ensure a Business Succession?

Athos Commemorative Services Acquires Les Espaces Memoria Inc.

Successful Case of Disguised Expropriation in Relation to a Heritage Protection By-Law

Disguised Expropriation in the Context of Environmental Protection

Strategic Forum on Market Consolidation and Business Succession

Four New Partners Appointed

Superior Court of Québec Addresses Reasonableness of Municipal Bylaws

BCF Partners with the Clinique Juridique de Saint-Michel to Promote Access to Legal Studies for Young People from Diverse Communities

The Superior Court Rules: A Municipality Cannot Prohibit Hunting on its Territory

Marie-Julie Lafleur Honoured as a Lexpert 2022 Rising Star

The Superior Court Has Invalidated a Municipal By-Law of the City of Mascouche

Must the City Pay for Storm Drain Repairs on Private Property Threatening to Collapse?

BCF Recognized in Legal 500 Canada Directory

The Illusory Discretion in Managing Culverts and Waterway Congestion

What’s the General Contractor’s Responsibility for Site Coordination?

Isabelle Landry and Audrey-Anne Béland, Co-authors of the Union des Municipalités du Québec’s Guide about Tourist Accomodation

Ocean Group Acquires a Major Shipyard and Increases its Capacity

Fight Against Future Pandemics: Jean Piette Appears Before the WHO

Five of our Lawyers Stand out in the 2023 Edition of the Chambers Canada Ranking

Ready to Bid? Be Sure to Read the Tender Documents Carefully

43 BCF Professionals Stand Out with 78 Nominations in the 2023 Editions of Best Lawyers in Canada and Ones to Watch

Why Did the Superior Court of Québec Stay Some Sections of Bill 96?

Do Municipalities Have the Authority to Limit the Distribution of Printed Publicity within their Boundaries?

Sportscene Group Becomes Grandio Group and Expands its Brand Portfolio

Can a General Contractor Significantly Increase Work Costs?

Seven New Lawyers Join BCF

Post-Pandemic Trends and Negotiations in Commercial Leasing

Adoption of Bill 96: What Are Your New Real Estate and Financing Obligations?

Adoption of Bill 96: Be Ready

Pride Month: The Value of Diversity

BCF, the 3rd Largest Law Firm in Québec

Canada’s Best Managed Companies: BCF Recognized for 15th Consecutive Year

Expropriation Compensation: How Far Does the “Highest and Best Use” Notion Extend?

Payment on Payment Clauses: Do You Know Your Rights?

BCF Stands Out in Benchmark Litigation Canada's 2022 Edition

BCF Welcomes Isabelle Métivier as a Real Estate Partner

lexpert

22 Professionals Stand Out in the Canadian Legal Lexpert Directory 2022

Court of Appeal Rules in Favour of Ville de Mont-Saint-Hilaire’s Real Estate Developers

Is Global Welfare Contingent on Deadlines?

BCF Welcomes Three New Partners

What Can a General Contractor Do to Be Relieved of His Duty to Advise?

How to Fight Back Against Pandemics

Plan and Specification Errors: Who’s to Blame?

Favourable Decision for Québec Oil and Gas Companies

BCF Recognized by the Globe and Mail as one of Canada’s top Law Firms

Who’s Who Legal 2021: 6 Partners Stand Out in Canada and Internationally

What Legal Recourse Do Citizens Have When Bothered by Municipal Work?

Important Victory for Développements St-Antoine in Fair and Equitable Expropriation Indemnity Case

A Major Transport Logistics Company Acquires SGT2000

"Acquisition, Expropriation and Tramway: How it Works" with Audrey-Anne Béland

Chambers Canada 2022: BCF Earned Band 1 Ranking in Québec for Corporate and Commercial Law

46 Lawyers of BCF Stand Out with 83 Recognitions in the 2022 Editions of Best Lawyers in Canada and Ones to Watch

Seven New Lawyers Join BCF

Victory in a Municipal Tax Dispute

Success in a Disguised Expropriation Case

Dismissal of a Class Action: How Far Does Police Liability Extend When Protesters Are Arrested?

Ouellet Group Acquires Roy Auto Group

Clarke Inc. completes the Acquisition of One-third Interest in a Real Estate Development Project

Our Partners Recognized in the 2021 Edition of Benchmark Litigation Canada Rankings

"A Risk of Expropriation That is Costly" with Isabelle Landry

Reform of the Environmental Permitting Regime: What You Need to Know

What Can Be Learned from Jurisprudential Developments in Public Contracts?

escalier

BCF Welcomes Seven New Lawyers

Highlights of the By-Law for a Diverse Metropolis

Supreme Court of Canada Takes Another Step towards the Guiding Principle of Good Faith in Contract Performance

Major Renovations: Avoid Having Your Acquired Rights Go To Dust

Minor Derogations: Major Victory in the Agricultural Field

Are you Aware of the Grey Areas for Minor Variances?

Hypertec Sells its Data Center Operations to Vantage Data Centers

Supreme Court Rules: Protection Against Cruel and Unusual Punishment Does Not Apply to Legal Persons

An ever denser metropolis and the "Not in my backyard" syndrome

Fundamental Changes Improve Federal Rental Support Program

Shaun E. Finn Co-author of the Annotated Code of Civil Procedure 2020-2021

Expropriation Demystified: What You Need To Know In Case of Expropriation Notice

Is It Possible to Successfully Challenge a COVID-19 Statement of Offence?

23 BCF Partners Ranked in the Canadian Legal Lexpert Directory

36 Lawyers of BCF Stand Out with 52 Nominations in the 2021 Edition of Best Lawyers in Canada

BCF Welcomes Six New Lawyers in its Team

Hengyun International Investment Commerce Inc. Decision: A New Approach to Landlord-Tenant Relationships Arising from the Pandemic

Isabelle Landry and Pierre Delisle, Co-Authors of Les projets immobiliers et les municipalités

Quebecor Sports and Entertainment acquires Théâtre Capitole

Details on Canada Emergency Commercial Rent Assistance (CECRA)

Corporate Environmental Governance in Quebec: Penalties and Defences

Quebec City Tramway Project: What Are the Rights of the Expropriated?

How to Avoid Penal Liability in Your Post-COVID Activities

Bill 61 on Economic Recovery: What Are the Impacts on the Environmental Obligations of Businesses?

Criminal Offences in the Construction Industry: The Hidden Consequences of a Guilty Plea and Good Practices

Commercial Leasing and Post-COVID-19: Trends and Negotiations to Expect

Will Public Bodies Join this Era of Local Procurement?

Businesses’ Environmental Obligations at a Time of Economic Reopening

Reform of the Environmental Permitting Regime in a Context of Economic Reopening

COVID-19: Solutions to Address this Situation

COVID-19: What Are the Implications for Corporate Environmental Obligations

COVID-19 and Construction: Impacts on Your Legal Hypothecs, RBQ Licences and Surety Bonds

Frequently Asked Questions about the Tramway Project

COVID-19: Impact of Measures Imposed By the Government of Québec on Municipalities

Allied Properties REIT acquires Centre de commerce mondial de Montréal

A Major $145 Million Investment for Alliance Magnesium

Municipal Law in Your Real Estate Transactions

BCF once again ranks as one of Montreal's Top Employers

Trudel Alliance Buys 7 Shopping Centres in Quebec City for $165M

Tourist Accommodation and Airbnb: Where Do We Stand?

BCF Names 16 New Partners for Its 25th Anniversary

Successful Judgment and Dismissal of a Claim Against Hydro-Québec and SEJB

Remember to Plan for Land Rehabilitation or for Management of Contaminated Soil in Your Projects

Are You a Leader or a Follower?Results of the Innovation Survey

The Autorité des Marchés Publics: What You Need to Know Regarding Major Projects and Request for Proposals

Environmental Impacts of Major Construction Projects: 5 Takeaways to Conduct Your Major Projects with Due Diligence

Major Public Infrastructure Projects: Where Is Culture in All This?

Infrastructure and Major Projects: Dare to Think Big

Will Your Construction Project Be Subject to an Environmental Assessment?

Obtaining Environmental Permits: Where to Start?

Taking the Powers of Cities Into Account When Developing Your Projects

Financing the Réseau Express Métropolitain: What About Transportation Dues?

Duties on the Transfer of Immovables in the Context of Major Projects

How to Deal With Changes During the Course of a Major Construction Project

Chambers Canada 2020: BCF Recognised in Corporate and Commercial Law

Strategic Forum on Innovation

Humania Assurance Acquires All the Assets of Tour+Med

5G Technology Is Coming: Legal Questions Abound

Best Lawyers in Canada: 22 BCF Lawyers Recognized

Pierre Delisle, Author of the 2nd Edition of La fiscalité locale : municipale, scolaire et régionale

BCF Represented Allied REIT in Two Major Acquisitions

Molson Brewery Purchased for $126 Million, BCF Part of the Transaction

Shaun E. Finn Co-author of the Annotated Code of Civil Procedure 2018-2019

Health Canada Is Changing its Cannabis Licensing Process

The AMP's New Extrajudicial Complaint System Is Underway!

16 BCF Partners Recognized in the Prestigious Canadian Legal Lexpert Directory

A $700 million project at the height of its ambitions

Cannabis and cryptocurrency businesses under the gaze of the Quebec Lobbyists Commissioner

Partner Julie Doré, Finalist for CREW M’s Excellence and Leadership Award

Can Municipalities Go this Far in their Rules Prohibiting Cannabis Use?

Cannabis and Zoning Issues

Municipal By-Laws in the Airbnb Era

BCF at the Heart of the Place Fleur de Lys Shopping Centre Acquisition in Québec City

rond-glasses-on-files-with-computer

What We Should Retain from the Recent Decisions of the Supreme Court of Canada

Get the latest thought leadership